Kollam

AMRUT – KOLLAM

KLM Allocation

Officers Responsible :

1. KLM_VR Raju V.R.Raju, Kollam Corporation Secretary

                       Mob :  9447413433 

                      Landline :  0474 – 2742724

                      email : secretarykollam@gmail.com 

2. Saji1 Saji.K.George, Urban Infrastructure Expert

3.   – Aswathy V S,  Urban Planner

PRESENT STATUS (As on 7Jun. 2019)

  Number of main projects Project Cost (Amount in Cr ) Total  projects (Including Subprojects) AS Accorded (No) AS accorded (Amount in Cr.) TS Issued (No) TS Issued (Amount in Cr.) Tendered
 (no)
Tendered (Amount in Cr.) Work awarded (No) Work awarded (Amount in Cr.) Work Completed (No) Expenditure (Amount in Cr) Expenditure % (Based on AS)
WATER SUPPLY 8 103.84 16 16 105.18 16 114.93 16 114.93 14 68.48 6 18.48 17.57%
SEWERAGE 3 87.74 5 5 42.66 5 39.80 5 39.80 0 0.00 0 0.00 0.00%
STORM WATER DRAINAGE 5 32.20 20 20 32.20 20 29.17 20 29.17 20 28.99 2 6.54 20.30%
URBAN TRANSPORT 9 24.44 12 12 21.92 12 20.69 12 20.69 10 10.18 1 0.59 2.71%
PARKS 5 5.23 7 7 5.23 7 3.31 7 3.31 7 3.25 1 1.95 37.24%
GRAND TOTAL 30 253.45 60 60 207.19 60 207.90 60 207.90 51 110.90 10 27.56 13.30%

 